Defective Wall Removal at Queensland Mine
A defective wall at a Queensland, Australia mine was removed by two Aquajet Aqua Cutter robots, reducing what would have been a six-month job to just four weeks.
About the Project
One of Australia’s leading Hydrodemolition specialist contractors, HiTech Industrial Services, has removed a defective section of blade wall from a mine in Mackay, Queensland using two Aquajet Aqua Cutter robots; a method that allowed continuous working despite the proximity of a railway line that placed restrictions on conventional demolition methods.
The Problem
The problem had arisen when an incorrect batch of concrete had been poured for a section of the blade wall measuring 9.3 m high by 9.3 m long and with a thickness of 1 m.
The Solution
Removal of the section was necessary, but had wire sawing techniques been used the deployment of the crane would have had to be scheduled around railway shutdowns.
“Using the two Aqua Cutter robots meant that our total time on-site was just four weeks, compared with an estimated six months or more that a crane and wire saw would have required,” says HiTech’s Operations Manager Damien Turner.
Equipment Used
HiTech – which was formed in 1991 specifically to pioneer and specialise in high pressure Hydrodemolition and water jetting services – used an Aqua Cutter 710V Evolution and an Aqua Cutter HVD-6000 from Sweden’s leading Hydrodemolition manufacturer, Aquajet Systems AB; delivered through local distributor, Adelaide-based Metco Ltd.
Reasons to use Rodeo
I’m in my final year doing Economics and I don’t know whether to apply for grad schemes now or do a masters first. What do you think?
Honest answer — it depends on where you want to end up. A lot of top grad schemes (Big 4, civil service, banking) don’t need a masters. Let’s look at the ones you’d be competitive for now, and we can decide if a masters actually adds anything.
Also worth knowing: most autumn 2026 applications are open now. Timing matters more than you think.
Start with a chat, not a search bar
Grad scheme, placement, apprenticeship? Not sure what you want yet — that's fine. Your agent talks it through with you and turns "I have no idea" into a shortlist.
Graduate Consultant — 2026 Scheme
Why you're a good match
StrongYour economics background and your summer at a regional bank line up with what PwC looks for on the consulting scheme. Applications close in four weeks.
See breakdownIt searches the market for you
Every day your agent scans the market matching roles against what actually matters to you, not just keywords on a CV.
Why you're a good match
You’ve got the grades and the economics background, and your bank internship is exactly the experience this scheme looks for. Apply soon — deadlines close within the month.
Experience fit
Your summer at the bank plus your econometrics coursework map directly to the day-one responsibilities on this scheme — client modelling, market briefings, and deal support.
Only hits
No noise. No "maybe this fits." Just roles with a clear explanation of why they're right — and where to focus when applying.
-
Aqua Cutter 710V Evolution
- Equipped with an 11m mast to enable it to comfortably reach the top of the wall.
- Designed for all horizontal, vertical, and overhead operations, having a 3-D positioning of the front power head; giving the operator full freedom to reach all areas and to work in confined areas.
-
Aqua Cutter HVD-6000
- Fitted with a standard 5 m mast.
- Similar 3-D feature as the 710V Evolution.
Safety Measures
“There was a 32,000 volt rail line behind the site that is used to transport coal. The line is just 2 m behind the wall,” says Mr Turner. “We proposed placing an 8mm thick steel plate behind the wall, which was supported by formwork and props, to prevent flying debris hitting the trains. It also stopped the jet from hitting the power cables.
“Apart from the speed and convenience of the removal rate using Hydrodemolition techniques, the idea of the 8mm safety shield helped us to win the contract. It was important that the trains continued working. A full trainload of coal is valued at 3 million A$, so it was important to ensure there were no delays.”


Get help with your application
Your very own career expert that helps elevate your application to the next level.
Project Timeline and Efficiency
Mr Turner says that although HiTech was on site for four weeks and working or on standby 24/7, the removal of the full 86m³ of defective concrete was achieved in just 172 blasting hours.
“There was a good deal of reorganising and other work going on at the site, and so much of our time was spent on active standby,” he said. “The actual work presented no unexpected problems for the Aquajet robots.”
Concrete Specifications
The concrete being removed was 40 MPa, with the reinforcing bars being 32 mm diameter with generally between 150 and 200 mm spacing, although in some places the spacing was only 50 mm.
Hydrodemolition Benefits
Use of Hydrodemolition ensured that the rebar was not damaged in any way whilst removing the defective concrete.
Mr Turner says that Hydrodemolition in Australia is still a relatively novel concept, but that with the technique proving to be so efficient, acceptance is spreading.